The financial plan

Built like a castle.
Pencils like a deal.

Funding status

Where the castle stands today

  • $929,000received to date
  • $6.5Mpending

The projected cost is $30.5 million. Four buckets of money cover it.

Where the money comes from

Sources of funds
Philanthropy$8.9MGifts, grants and sponsorships, including naming gifts.
Tax credits + easement$16.9MInvestors buy the tax credits UAA syndicates, such as the 9% housing credit (LIHTC), historic credits (HPTC), sustainability credits and New Markets Tax Credits (NMTC). A historic preservation easement adds more.
Public funds$3.3MGrants and contributions from public agencies.
Loans$1.45MThe city housing loan request (HDLP).

Where the money goes

Uses of funds
Homes$12.8M32 affordable homes.
Chapel$4.5MRestoration of the 1904 building.
Parking$4.2MTwo levels of parking.
Pre-development$1.73MDesign, engineering, permits, legal, insurance and owner costs.
Sculpture garden + art$0.43MLandscape and public realm, plus attraction installation and art.
Land$1.87MSite acquisition and payoff of the existing mortgage.
Contingency$2.24MConstruction reserve.
Solar + battery$1.06MRooftop solar and battery storage for the homes and the art center.
Developer fee$1.0MDevelopment services for the homes and the art center.
Site, furnishings + other$0.64MSite work and utilities, environmental assessment, furnishings and a financing reserve, net of materials-tax savings.

Why gifts come first

Gifts light the first spark. Studies, design and permits come before any tax credit or bond pays out, so gifts and community-development loans fund those first steps. Every naming gift and sponsorship moves the castle forward. Tax credits and bonds step in once construction financing closes.